Status operasional unit pembangkit
Kapasitas daya yang tersedia
Nama Unit | Mesin | DMN | DMP | Beban | Status | Progres | Waktu Update |
---|---|---|---|---|---|---|---|
PLTU MORAMO ( Subsistem Kendari ) | MORAMO #1 | 50.0 | 50.0 | 47.0 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTU MORAMO ( Subsistem Kendari ) | MORAMO #2 | 50.0 | 50.0 | 46.7 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTD Wua Wua | MAK #1 | 1.7 | 1.7 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Wua Wua | MAK #2 | 1.6 | 1.6 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Wua Wua | MAK #3 | 1.7 | 1.7 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Wua Wua | Mak #4 | 1.7 | 1.7 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Wua Wua | MAK #5 | 1.3 | 1.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Poasia | MIRR #1 | 0.0 | 1.4 | 0.0 MW | ❓ Overhaul |
Pemeliharaan top overhaul progress .....
|
28/04/2025 09:39:44 |
PLTD Poasia | MIRR #2 | 0.0 | 1.4 | 0.0 MW | 🔧 Pemeliharaan |
Penggantian main bearing dan crankpin bearing (OK)
Penggantian rubber coupling (OK)
Pengukuran defleksi (NO 1 = +5,25)
|
28/04/2025 09:39:44 |
PLTD Poasia | MIRR #4 | 0.0 | 0.0 | 0.0 MW | 💤 Mothballed |
Menyaipakan kelengkapan material
|
28/04/2025 09:39:44 |
PLTD Poasia | MIRR #5 | 1.7 | 1.4 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Poasia Containerized | CUMS #1 | 1.0 | 0.9 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Poasia Containerized | CUMS #2 | 1.0 | 0.9 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Poasia Containerized | CUMS #3 | 1.0 | 0.9 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD Kolaka | DHS #1 | 0.4 | 0.4 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Kolaka | DHS #2 | 0.4 | 0.4 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Kolaka | DHS #3 | 0.3 | 0.3 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Kolaka | NIGATA #3 | 0.3 | 0.5 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Kolaka | MAK #1 | 1.8 | 1.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Kolaka | MAK #2 | 1.8 | 1.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Lanipa Nipa | DEUTZ BV #2 | 0.7 | 0.7 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Lanipa Nipa | DEUTZ BV #3 | 0.0 | 0.0 | 0.0 MW | ⚠️ Gangguan |
1. Pembongkaran turbocharger (Selesai)
2. Mobilisasi turbocharger ke workshop (28 Feb 25)
3. Assesment turbocharger (Menunggu hasil assesment dari workshop sementara proses bongkar dan koordinasi bag enji UP (apakah layak direkondisi levering time 4 bulan atau pengadaan baru levering time 12 bulan)
4. Pengadaan baru/rekondisi turbocharger
5. Levering rekondisi turbocharger
6. Mobilisasi turbocharger ke site
7. Instal turbocharger
8. Final Check dan Running Test
UPDATE 08/04/2025
- CT71 ( Telah dilakukan pengecekan dan pengukuran kondisi Oke ) sisa menunggu material ( estimasi waktu selesai M1 Mei 25 )
- CT72 Turbo kondisi hasil pemeriksaan masih bisa di perbaiki menunggu info dari sentral Turbo ( PIC Enijiniring )
|
28/04/2025 08:40:00 |
PLTD Lanipa Nipa | DEUTZ BV #4 | 0.8 | 0.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Lanipa Nipa | MAN #1 | 0.4 | 0.4 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Ladumpi | YANMAR #1 | 0.2 | 0.2 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Ladumpi | YANMAR #2 | 0.2 | 0.2 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTD Ladumpi | CUMS #2 | 0.0 | 0.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTM Sabilambo | ZJG #1 | 1.0 | 1.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:40:00 |
PLTM Sabilambo | ZJG #2 | 1.0 | 1.0 | 1.0 MW | ⚡ Operasi |
|
28/04/2025 08:40:00 |
PLTM Mikuasi | MIKUASI #1 | 0.5 | 0.5 | 0.4 MW | ⚡ Operasi |
|
28/04/2025 08:40:00 |
PLTD Bau Bau | DHS #3 | 0.8 | 0.5 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Bau Bau | DHS #4 | 0.8 | 0.5 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Bau Bau | DEUTZ BV #1 | 0.8 | 0.7 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Bau Bau | DEUTZ BV #2 | 0.0 | 0.6 | 0.0 MW | 🔧 Pemeliharaan |
|
28/04/2025 08:54:36 |
PLTD Bau Bau | DEUTZ BV #3 | 0.7 | 0.5 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Pasarwajo | CUMS #1 | 0.0 | 0.9 | 0.0 MW | 🔧 Pemeliharaan |
- unit sudah mengirimkan lh-05 dan laporan investigasi awal
- Pembongkaran generator (3 Mar 25)
- Mobilisasi generator ke workshop (6 Mar 25)
- Rewinding generator est. M4 Apr 25
- Pengiriman kembali generator ke pasarwajo est. M4 Apr25
- Instal generator est M2 Mei 25
- running test est M2 Mei 25
|
28/04/2025 08:54:36 |
PLTD Pasarwajo | CUMS #2 | 1.0 | 0.9 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTM Winning | BWTR #1 | 0.8 | 0.8 | 0.7 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTM Winning | BWTR #2 | 0.8 | 0.8 | 0.7 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD Raha | DHS #3 | 0.4 | 0.4 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | MIRR | 1.8 | 1.6 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | DEUTZ BV #1 | 0.0 | 0.6 | 0.0 MW | ⚠️ Gangguan |
1. Pengecekan exhaust manifold sisi turbocharger (16 Okt 24)
2. Pengecekan cylinder head no.3 dan 8 (16 Okt 24)
3. Pembongkaran turbocharger (16 Okt 24)
4. Pembongkaran cylinder head no.3 dan 8 (16 Okt 24)
5. Inventarisasi kebutuhan material pemulihan (17 Okt 24, surat 20 Januari 2025)
6. Pengadaan Material Permulihan (Nodis ke ICC 0256 - 19 Feb 25)
7. Perbaikan/Rekondisi turbocharger (Sudah tiba diworkshop kendala tools sementara dicarikan)
8. Perbaikan/Rekondisi cylinder head (Onprogres)
9. Instal Material Pemulihan (material levering material est 3-4 bulan)
10. Running Test est M4 Jun 2025"
|
28/04/2025 08:54:36 |
PLTD Raha | CUMS #1 | 0.8 | 0.9 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | CUMS #2 | 0.8 | 1.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | CUMS #3 | 0.8 | 0.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | CUMS #4 | 0.8 | 0.9 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | CUMS #5 | 0.0 | 0.9 | 0.0 MW | ⚠️ Gangguan |
1. Pengecekan axial conrod semua cyl (finish)
2. Pembongkaran Conrod Cyl No.2A dan No.2B (finish)
3. Pembersihan crankpin journal No.2 (finish)
4. Polishing crankpin journal No.2 (finish)
5. Assessment crankshaft bidang Enj UP (hasil spot check ditemukan crack)
6. Terdapat opsi pemanfaatan equipment dari PLTD Gunung Sitoli mesin KTA 50 G3 yang berstatus ATTB, perlu dikaji lebih lanjut relokasi material internal UP (sudah bersurat ke Ditgas terkait kajian pemanfaatan material tgl 1 Nov)
7. Assessment oleh PT ALTRAK (hasil masih layak untuk 1 unit complete dan 1 unit sudah tidak complete namun crankshaft masih layak pakai) 30-Jul-24
8. Relokasi Material dari PLTD Gunung Sitoli ( koordinasi dengan tim altrak medan untuk pengambilan material crankshaft dan blok )
9. Proses penyusunan kebutuhan material pemulihan diluar scope OH (18 Jan 25)
10. Kontrak khs overhaul sudah terbit dan sudah diterbitkan DO , rencana dibarengkan pelaksanaan Final Stage (19 Mar 25)
11. Generator diambil atasi ggn unit 4 (penyusunan DRP rekondisi generator eks unit 4)
|
28/04/2025 08:54:36 |
PLTD Raha | MITS #1 | 0.9 | 1.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | MITS #2 | 0.0 | 0.0 | 0.0 MW | 💤 Mothballed |
1. sudah bersurat ke UP Kendari Tanggal 18 November 2024, penyampain gangguan, laporan investigasi, BA. Material terpakai di unit lain dan List material kebutuhan pemulihan mesin tersebut. (material sdh banyak di manfaatkan ke unit lain)
2. Rewinding generator ex-wangi - wangi 28 Feb 25
3. Rewinding Trafo ex-wangi - wangi (proses packing) est. M2 Mar 25
4. Perlu dikaji lebih lanjut oleh internal UP terkait opsi RU krn secara fisik sdh, equipment sdh banyak pindah
5. Nota Dinas Har ke Enj (8-Okt-24)
6. Update kembali Inventarisasi kebutuhan material pemulihan dengan mengoptimalisasi material eks overhaul (Permintaan PH)
|
28/04/2025 08:54:36 |
PLTD Raha | MITS #4 | 0.7 | 0.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD Raha | MITS #3 | 0.0 | 0.0 | 0.0 MW | 💤 Mothballed |
1. Pemeriksaan Axial Conrod (27 Des 22)
2. Pembongkaran Conrod Cyl No.5 (27 Des 22)
3. Pembersihan crankpin journal No.5 (27 Des 22)
4. Polishing crankpin journal No.5 (27 Des 22)
5. Telah menyurat tanggal 29 Januari 2025 terkait list kebutuhan material
6. Klaim Garansi ke pihak pelaksana terkait Crankshaft (selesai)
7. Pengiriman crankshaft pengganti dan sebagian material pemulihan dari pihak pelaksana (onprogres)
8. Rewinding Generator sudah tiba (28 Feb 25)
9. Perbaikan Block Engine di workshop (28 Jan 25)
10. Kesepakatan Pelaksanaan Jasa untuk permulihan (selesai)
11. Proses penyusunan kebutuhan material pemulihan, sementara koordinasi kebeberapa pelaksana opsi tercepat (levering material paling lama 3-4 bulan)
12. Tim ITI akan tiba disite est M1 Mar 25 (belum ada informasi lebih lanjut)
13. Running Test est M4 Juni 25
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | DHS #1 | 0.4 | 0.2 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | DHS #2 | 0.3 | 0.1 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | SWD #1 | 0.3 | 0.2 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | SWD #2 | 0.3 | 0.2 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | SWD #3 | 0.2 | 0.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | CUMS 1 | 0.9 | 0.8 | 0.6 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | CUMS 2 | 1.0 | 0.9 | 0.8 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | MITS #1 | 0.0 | 0.8 | 0.0 MW | ⚠️ Gangguan |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | MITS #2 | 1.0 | 0.0 | 0.8 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | MITS #3 | 1.0 | 0.5 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | MITS #4 | 1.0 | 0.9 | 0.8 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | MITS #5 | 1.0 | 0.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD WANGI-WANGI ( SIstem Isolated Wangi-Wangi ) | MITS #6 | 1.0 | 0.7 | 0.7 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD LANGARA ( Isolated Sistem Langara ) | CUMS #1 | 0.5 | 0.5 | 0.4 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTD LANGARA ( Isolated Sistem Langara ) | CUMS #2 | 0.5 | 0.5 | 0.4 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTD LANGARA ( Isolated Sistem Langara ) | CAT | 0.2 | 0.1 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD LANGARA ( Isolated Sistem Langara ) | MAN #1 | 0.3 | 0.3 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD LANGARA ( Isolated Sistem Langara ) | MAN #2 | 0.4 | 0.3 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD LANGARA ( Isolated Sistem Langara ) | MITS #1 | 1.0 | 1.0 | 0.9 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTD LANGARA ( Isolated Sistem Langara ) | MITS #2 | 0.9 | 1.0 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTD EREKE ( Sistem Isolated Ereke ) | DHS #3 | 0.4 | 0.3 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD EREKE ( Sistem Isolated Ereke ) | DHS #6 | 0.2 | 0.2 | 0.0 MW | 🔆 Standby |
|
28/04/2025 08:54:36 |
PLTD EREKE ( Sistem Isolated Ereke ) | DHS #7 | 0.4 | 0.4 | 0.3 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD EREKE ( Sistem Isolated Ereke ) | DHS #9 | 0.3 | 0.3 | 0.3 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD EREKE ( Sistem Isolated Ereke ) | CUMS #1 | 0.9 | 0.9 | 0.7 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD EREKE ( Sistem Isolated Ereke ) | CUMS #2 | 0.4 | 0.0 | 0.4 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTD EREKE ( Sistem Isolated Ereke ) | CUMS #3 | 0.0 | 1.0 | 0.0 MW | 🔧 Pemeliharaan |
|
28/04/2025 08:54:36 |
PLTMG KENDARI ( Subsistem Kendari ) | WARTSILA #1 | 8.0 | 9.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTMG KENDARI ( Subsistem Kendari ) | WARTSILA #2 | 8.0 | 9.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTMG KENDARI ( Subsistem Kendari ) | WARTSILA #3 | 8.0 | 9.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTMG KENDARI ( Subsistem Kendari ) | WARTSILA #4 | 8.0 | 9.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTMG KENDARI ( Subsistem Kendari ) | WARTSILA #5 | 8.0 | 9.8 | 0.0 MW | 🔆 Standby |
|
28/04/2025 09:39:44 |
PLTMG KENDARI ( Subsistem Kendari ) | WARTSILA #6 | 8.0 | 9.8 | 6.0 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTU BARUTA ( Sistem Bau-Bau ) | BARUTA #1 | 6.0 | 6.0 | 5.6 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTU BARUTA ( Sistem Bau-Bau ) | BARUTA #2 | 6.0 | 6.0 | 5.5 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTMG BAU-BAU ( Sistem Bau-Bau ) | UNIT #1 | 9.8 | 9.8 | 6.2 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTMG BAU-BAU ( Sistem Bau-Bau ) | UNIT #2 | 9.8 | 9.8 | 6.2 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTMG BAU-BAU ( Sistem Bau-Bau ) | UNIT #3 | 9.8 | 9.8 | 6.2 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTMG BAU-BAU ( Sistem Bau-Bau ) | UNIT #4 | 9.8 | 9.8 | 6.2 MW | ⚡ Operasi |
|
28/04/2025 09:39:44 |
PLTM RONGI | UNIT #1 | 0.4 | 0.4 | 0.3 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |
PLTM RONGI | UNIT #2 | 0.4 | 0.4 | 0.3 MW | ⚡ Operasi |
|
28/04/2025 08:54:36 |